Line Clearance Permit policy (LCP)

Aldridge has an established line clearance work site permitting policy for any overhead line within 50 feet or less. This policy helps to protect our employees from the hazard of line contact. The procedure includes analyzing a job site with any overhead lines, completing the permit application, and then submitting to electrical hazard experts at corporate headquarters for approval. These applications (nearly 2,000 yearly) are processed within 24 hours, giving immediate attention to emergency situations, so that work can begin.

The LCP goes beyond our Daily Task Analysis (DTA) and acts as a self-discipline tool for electricians to always be aware of their surroundings and the dangers present when working near energized electrical lines. This Aldridge-mandated policy adds value to the personal safety of our people.